Licence to generate electricity - Willmount Ltd (Castlecraig Wind Farm)

29 November 2017

Grant of licence to generate electricity to Willmount Limited.

On 23 October 2017 the Utility Regulator issued a public consultation on the proposed grant of an electricity generation licence to Willmount Limited at Castlecraig Wind Farm.

We did not receive any formal responses to the proposal to grant a licence to Willmount Limited.

In accordance with Article 10 of The Electricity (Northern Ireland) Order 1992, the Utility Regulator now gives notice that a licence for the generation of electricity in Northern Ireland was granted to Willmount Limited on 28 November 2017.