Approval of Moyle Interconnector Access Rules and Charging Methodology Statement

On 21 July 2017, Moyle Interconnector Limited (MIL) submitted to the Utility Regulator (UR) proposals for modified access rules (the Moyle Access Rules) and a modified charging methodology (the Moyle Charging Methodology) for the Moyle interconnector.

The Moyle Access Rules set out the general terms and conditions that a user must accept to obtain access to and use capacity on Moyle interconnector.

On 17 November 2017, the UR approved the Moyle Access Rules and the Moyle Charging Methodology on the basis that they meet the relevant access rules and charging methodology objectives.

Help viewing documents